A group of four tramways in the Sylhet District were surveyed in 1897-98. By 1906 the report shows that only part of one of the four tramways was in progress -

The other proposals were not apparently adopted.[1]

  • Sutang to Madna, reconnoitred in 1898 – 30 miles
  • Srimangal to Manumukh, reconnoitred in 1898 – 22 miles
  • Kalaura via Sylhet to Chhatak, reconnoitred in 1898 – 53 miles
  • Karimganj to Chandi Khira,with branch from Pathar Kandri Bazar to Magura Cherra, reconnoitred in 1897 – 43 miles