Scinde Railway: Difference between revisions
→Personnel: sub heading created 'Joseph Harrison' added |
'Robert Stephenson' info added |
||
Line 12: | Line 12: | ||
The Company had been invited to tender in 1855 by the [[Government of India]] to build a railway from [[Karachi|Kararchee(Karachi)]] to [[Hyderabad]], to be called the '''Scinde Railway''' <ref> British Library IOR/L/F/8/10 (853) ‘Contract to build a railway from Kararchee to Hyderabad’, 1855 </ref>, this being a distance of about 120 miles(192km). The company contracted with the Government of India ([[Government of India |GoI]]) to construct the initial section from [[Karachi]] to [[Kotri]]. The company was granted a 5% return on investment up to a maximum of £1 million in order to build the ‘120 mile’ line <ref name=name> [https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/228649/8330.pdf H.M. Government “Statute Law Repeals: Nineteenth Report : Draft Statute Law (Repeals) Bill; April 2012"; pages 134-135, paragraphs 3.78-3.83] Retrieved on 2 January 2016</ref>. | The Company had been invited to tender in 1855 by the [[Government of India]] to build a railway from [[Karachi|Kararchee(Karachi)]] to [[Hyderabad]], to be called the '''Scinde Railway''' <ref> British Library IOR/L/F/8/10 (853) ‘Contract to build a railway from Kararchee to Hyderabad’, 1855 </ref>, this being a distance of about 120 miles(192km). The company contracted with the Government of India ([[Government of India |GoI]]) to construct the initial section from [[Karachi]] to [[Kotri]]. The company was granted a 5% return on investment up to a maximum of £1 million in order to build the ‘120 mile’ line <ref name=name> [https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/228649/8330.pdf H.M. Government “Statute Law Repeals: Nineteenth Report : Draft Statute Law (Repeals) Bill; April 2012"; pages 134-135, paragraphs 3.78-3.83] Retrieved on 2 January 2016</ref>. | ||
The London based [[Robert Stephenson]], Consultant Engineer was approached by the 'Scinde Raimway Company' for advice <ref>[https://books.google.fr/books?id=BzErDwAAQBAJ&pg=PA155&lpg=PA155#v=onepage&q&f=false Google Books "Robert Stephenson – The Eminent Engineer” edited by Michael R. Bailey; page 155-57]; Retrieved 4 May 2020</ref>. The exact date, extent and content of this consultation is not known but would be in the early 1850's | |||
[[File:Scinde Railway Company - Lines.png|thumb|File:Scinde Railway Company - Lines]] | [[File:Scinde Railway Company - Lines.png|thumb|File:Scinde Railway Company - Lines]] |
Revision as of 07:50, 5 May 2020
Scinde Railway also known as the Karachi-Kotri (Indus River) Railway
– this was the first railway of the Scinde Railway Company - see separate page for further information on the formation and development of the Company
Note
- Some documents and references refer to the ‘Sind Railway’ which is not the correct spelling.'
- Not to be confused with the ‘Sind Light Railway’ which is a separate narrow gauge railway.
Background
The Scinde Railway Company was first established by deed of settlement in March 1855 and incorporated by the ‘Scinde Railway Act’ of Parliament in July 1855 after which a contract was entered with the East India Company in December 1855.
The Company had been invited to tender in 1855 by the Government of India to build a railway from Kararchee(Karachi) to Hyderabad, to be called the Scinde Railway [1], this being a distance of about 120 miles(192km). The company contracted with the Government of India (GoI) to construct the initial section from Karachi to Kotri. The company was granted a 5% return on investment up to a maximum of £1 million in order to build the ‘120 mile’ line [2].
The London based Robert Stephenson, Consultant Engineer was approached by the 'Scinde Raimway Company' for advice [3]. The exact date, extent and content of this consultation is not known but would be in the early 1850's
The 'Scinde Railway' was one part of a communication link developed by the 'Scinde Railway Company' constructed primarily to reduce the journey time on the final stage of long haul from Britain to Delhi and Calcutta. The line from Karachi to Kotri could move cargo and passengers to Kotri instead of Karachi, saving approx 250km of circuitous journey through Indus River delta. At Kotri the line linked to the ’Indus Flotilla’ Company steamers, also owned by the Scinde Railway Company which operated upstream to Multan [4]. From Multan the ‘Punjaub Railway ’ ran to Amritsar where it became the ‘Delhi Railway’, both owned by the Scinde Railway Company, connected to the East Indian Railway at Ghaziabad (just east of Delhi), thus providing a connection between Karachi and Delhi and onward to Calcutta.
Construction
The work commenced in April 1858 to construct the broad gauge(BG) single track railway [5] and on 13 May 1861 succeeded in connecting the port town of Karachi to Kotri on the Indus River, the first railway line for public traffic between these towns [6].
The challenges faced during the construction were considerable as described in the article “Karachi to Kotri - The first railways in Pakistan” by Owais Mughal Cite error: Invalid parameter in <ref>
tag
Records
An on-line search of the India Office Records (IOR) records held at the British Library relating to this railway [7] gives the following:-
- Z/E/4/25/I53; “Indus River, Railway line to be constructed from Karachi to a point on.”; 1854-55
- Z/E/4/25/R766; “Rivers, Indus, Railway line to be constructed from Karachi to a point on.”; 1854-55
- L/AG/46/17/1-13; “1. Scinde Railway Company”; 1855-1878
Personnel
Construction Engineering Management
- John Brunton; 1857, Appointed Chief Resident Engineer of Scinde Railway (Sind Railway) [8]; 1858-62, 'Supervised the construction of the 108 miles(174km) of the Scinde Railway between Karachi and Kotri until its completion in 1862. His detailed "Description of the line and works of the Scinde Railway" [9] itemise the problems of building in the tropics.'
- William Arthur Brunton, the son of the above; 1857 at age 17, Assistant Engineer; then Area Surveyor on the Scinde Railway; 1859-1961, responsible for the erection of the thirty-two 45 foot (13.7M) spans of the 'Bahrun Valley Viaduct' [8]. This is the longest bridge on the Karachi-Kotri section and is a viaduct across the Bahrun River. Construction on this bridge was started on 5 March 1859 and completed on 26 January 1861 [4]
- Willoughby Charles Furnivall District Engineer in charge of construction under John Brunton c.1860-7 [10].
Construction Staff - Other staff of the Scinde Railway involved during the construction are acknowledged:-
- J E Hartley; c.1859-c.1861, ‘Scinde Railway’ Resident Engineer supervising the 'Mulleer Railway Viaduct' construction [11]
- W T Warren [12]
- Mr Thomas Warren [12]
- Mr J Pinder [12]
Railway Operations Management
- Joseph Harrison, 1860-75, Engineer-in-Chief, General Agent and General Agent for some part of this time [13]. 1864-1870 Chief Resident Engineer during construction of ‘Delhi Railway’[14].
Historical books online
- "The Scinde railway, and its relations to the Euphrates valley, and other routes to India" by W P Andrews, Chairman of the Scinde Railway Company 1856 Google Books
- "Report of proceedings of an extraordinary general meeting of the Scinde Railway Company, held on Friday the 24th July, 1857" Google Books
- "Description of the Line and Works of the Scinde Railway" by John Brunton. 1863. Google Books
Further Information
See Scinde Railway Company, Indus Flotilla, Punjaub Railway and Delhi Railway
and Scinde, Punjaub & Delhi Railway following amalgamation in 1870 until 1886
and North Western Railway from 1886 when the line became part of the ‘NWR Mainline’
References
- ↑ British Library IOR/L/F/8/10 (853) ‘Contract to build a railway from Kararchee to Hyderabad’, 1855
- ↑ H.M. Government “Statute Law Repeals: Nineteenth Report : Draft Statute Law (Repeals) Bill; April 2012"; pages 134-135, paragraphs 3.78-3.83 Retrieved on 2 January 2016
- ↑ Google Books "Robert Stephenson – The Eminent Engineer” edited by Michael R. Bailey; page 155-57; Retrieved 4 May 2020
- ↑ 4.0 4.1 All Things Pakistan “Karachi to Kotri - The first railways in Pakistan” by Owais Mughal, Posted on September 17, 2009; Retrieved on 23 Feb 2018
- ↑ Sind Gazette British Library Compiled by E H Atkin Bombay Salt Department. Printed for government at the Steam Press Karachi 1907 Page 344
- ↑ Grace’s Guide “Scinde Railway” Retrieved on 2 January 2016
- ↑ “British Library Archives and Manuscripts Catalogue” - Search; Retrieved 8 Apr 2016
- ↑ 8.0 8.1 Google Books "The Archaeology of an Early Railway System: The Brecon Forest Tramroads" by Stephen Hughes, page 126; Retrieved 14 Jun 2016
- ↑ Minutes of the Proceedings of the Institution of Civil Engineers, Volume 22, January 1863, pages 451-"Description of the line and works of the Scinde Railway" by John Brunton; Retrieved 14 Jun 2016
- ↑ Institution of Civil Engineers "Biographical Dictionary of Civil Engineers in Great Britain and Ireland - Furnivall, Willoughby Charles"; Retrieved on 21 Jul 2016
- ↑ Google Books ‘The Line and Works of the Scinde Railway’ by John Brunton, Institution of Civil Engineers, 1862-63 Page 23 ; Retrieved 19 Feb 2018
- ↑ 12.0 12.1 12.2 Google Books ‘The Line and Works of the Scinde Railway’ by John Brunton, Institution of Civil Engineers, 1862-63 Page 25 ; Retrieved 19 Feb 2018
- ↑ Grace's Giude "Joseph Harrison"; Retrieved 1 Mar 2018
- ↑ Google Books “Life and Labours of Thomas Brassey” by Arthur Helps; pages 148-149; Retrieved 1 Mar 2018